Footing Calculator

Isolated footings spread a column’s load into the ground. Each usually sits on a thin bed of plain cement concrete (PCC). This calculator gives the concrete for all footings and the PCC bed.

Measure in
Results update as you type.

Cement

22 bags

21.92 bags of 50 kg for 2.72 m³ of M20

Footing concrete
2.72 m³ (96 cft)
Sand
1.14 m³ (40.3 cft)0.4 brass
Aggregate (gitti)
2.28 m³ (80.6 cft)0.81 brass
Water (approx.)
548 litreswater–cement ratio 0.5
PCC bed (M7.5, 75 mm wider each way)
0.86 m³ (30.3 cft)2.9 more bags of cement

Nominal mixes are for estimating. Structural concrete should follow the engineer’s design mix. Add 3% to 5% for wastage.

About this calculator

Enter one footing’s size and depth and the number of footings.

How to use it

  1. Choose feet or metres and enter the dimensions.
  2. Choose the mix or materials.
  3. Read the quantities to order.

The formula

Footing volume = length × width × depth × number
PCC bed
M7.5, 75 mm wider on each side

Worked example

Six footings of 4 × 4 ft, 12 in deep, on a 3 in PCC bed

  1. Footing concrete = 1.22 × 1.22 × 0.305 × 6 = 2.72 m³ (96 cft).
  2. M20 needs about 22 bags of cement.
  3. The PCC bed adds 0.86 m³.

What the result means

Stepped or sloped footings need their parts calculated separately.

Concrete for one footing of common sizes

Results from the calculator for a single footing in M20 (1:1.5:3) on a 3 inch M7.5 PCC bed. Multiply by the number of footings, or enter the count directly so the bags are rounded only once.

One footing, M20, 3 in PCC bed
Size and depthConcreteCement (M20)SandAggregatePCC cement
3 × 3 ft, 12 in9 cft2.06 bags3.8 cft7.6 cft0.3 bags
4 × 4 ft, 12 in16 cft3.65 bags6.7 cft13.4 cft0.5 bags
4 × 4 ft, 18 in24 cft5.48 bags10.1 cft20.2 cft0.5 bags
5 × 5 ft, 18 in37.5 cft8.56 bags15.8 cft31.5 cft0.7 bags
6 × 6 ft, 18 in54 cft12.33 bags22.7 cft45.4 cft1 bag

How the grade changes the cement

For six footings of 4 × 4 ft and 12 in deep (96 cft of concrete), the calculator gives 17.22 bags at M15, 21.92 bags at M20 and 30.14 bags at M25. The sand and aggregate fall slightly as cement rises. Use the grade on your structural drawing; the nominal mixes here are for estimating.

Before and during the pour

  • Check the pit size and depth against the drawing, and remove loose soil from the bottom before laying PCC.
  • Let the PCC bed set before placing the reinforcement mesh, and use cover blocks so the steel does not touch the PCC.
  • Pour each footing in one go and compact it with a vibrator or rodding.
  • Keep the footing moist while it cures before backfilling around it.

Assumptions

  • Rectangular footings with flat tops.

Limitations

  • Footing size and reinforcement must come from a structural design.

Frequently asked questions

What thickness is PCC under a footing?

Commonly 75 to 150 mm.

Which grade for footings?

M20 or as the engineer specifies.

Is excavation included?

No; use the soil calculator for digging.

How many cement bags for a 4 × 4 ft footing?

About 3.65 bags of M20 for a 12 in deep footing and about 5.48 bags at 18 in deep, plus about 0.5 bags for a 3 in PCC bed.

Why is the PCC bed larger than the footing?

The calculator makes it 75 mm wider on each side, which gives a clean, level base with room to set the formwork and reinforcement.