Brick Calculator

Estimate the bricks for a wall and the cement and sand for the mortar between them. Choose a full-brick (9 inch) or half-brick (4½ inch) wall, and modular or the common Indian brick size.

Measure in
Wall thickness
Results update as you type.

Bricks needed

2,033

1,935 + 5% wastage

Cement for mortar
5.6 bags
Sand for mortar
1.18 m³ (41.5 cft)0.42 brass
Brickwork volume
4.46 m³ (157.5 cft)
Bricks per m³
434

About this calculator

Deduct doors and windows to avoid over-ordering.

How to use it

  1. Choose feet or metres and enter the dimensions.
  2. Choose the mix or materials.
  3. Read the quantities to order.

The formula

Bricks = brickwork volume ÷ volume of one brick with 10 mm mortar
common brick
230 × 110 × 70 mm, 434 per m³
modular brick
190 × 90 × 90 mm, 500 per m³

Worked example

A 20 × 10 ft full-brick wall, common bricks

  1. Brickwork = 18.58 m² × 0.24 m = 4.46 m³.
  2. Bricks = 4.46 × 434 = 1,935, or 2,033 with 5% wastage.
  3. Mortar at 1:6 needs about 5.6 bags of cement and 1.18 m³ of sand.

What the result means

Brick sizes vary between kilns; measure a few and use the closest option.

Bricks, cement and sand per 100 sq ft of wall

Calculator results for a plain 10 × 10 ft wall, 10 mm joints and 5% wastage on bricks.

Per 100 sq ft of wall, no openings
Wall and brickBricks (with 5%)Cement at 1:4Cement at 1:6Sand at 1:6
4½ in, common 230 × 110 × 70 mm5092.0 bags1.4 bags10.4 cft
9 in, common 230 × 110 × 70 mm1,0174.0 bags2.8 bags20.8 cft
Half brick, modular 190 × 90 × 90 mm4881.6 bags1.2 bags8.6 cft
Full brick, modular 190 × 90 × 90 mm9763.3 bags2.3 bags17.2 cft

Checking brick quality on site

  • Ring test: strike two bricks together. A well-burnt brick gives a clear metallic ring; a dull thud suggests under-burnt brick.
  • Scratch test: a fingernail should not leave a mark on a good brick.
  • Shape: edges should be straight and sharp, faces flat, and the colour even across the stack.
  • Soak bricks in water before laying and let the surface dry slightly. A dry brick sucks water out of the mortar and weakens the joint.

First-class and second-class bricks, and ordering

First-class bricks are well burnt, uniform in size and colour, and have sharp edges, so they suit exposed brickwork and load-bearing walls. Second-class bricks may be slightly uneven in shape or colour; they are often used where the wall will be plastered. Bricks are usually priced and delivered per thousand, so round the calculator's figure up to the next lot your supplier sells, and count the delivery before unloading is signed off.

Assumptions

  • 10 mm mortar joints.

Limitations

  • Lintels, beams and openings must be deducted.

Frequently asked questions

How many bricks in 1 m³?

About 434 common bricks or 500 modular bricks.

How many bricks per sq ft for a 9 inch wall?

About 9 to 10.

What mortar mix for brick walls?

1:6 for full-brick walls, 1:4 for half-brick walls.

How much cement is needed for 100 sq ft of brickwork?

With common bricks, about 2.8 bags for a 9 inch wall in 1:6 mortar and about 2 bags for a 4½ inch wall in 1:4 mortar.

Why are bricks soaked before laying?

A dry brick absorbs water from the fresh mortar, so the mortar does not set properly and the bond is weak. Soaking first keeps the water in the mortar.

Last reviewed on 12 October 2026. How we calculate and check. Found a mistake? Tell us.